Separate the two evidence routes
Product air-permeability information describes a tested window configuration under stated conditions. Building airtightness testing assesses a much wider enclosure. Ask which opening type and dimensions the product evidence covers. Then identify the perimeter connection, adjoining air-barrier materials and other penetrations that must be coordinated on site.
Draw a continuous air barrier
Trace the intended air-sealing layer from the wall to the window frame on each detail. Include corners, sill supports, bracket penetrations and transitions between materials. Assign installation responsibility and confirm compatible products. A foam-filled joint should not be assumed to provide the specified continuous air barrier without an approved sealing detail.
Schedule checks while repairs remain practical
Agree whether intermediate inspection or an early enclosure test is appropriate for the project. Keep the relevant joints visible until the agreed checks are completed. If leakage is found, record its location and obtain a suitable repair method. Closing finishes before the connection is checked can make correction disproportionately disruptive.
Information to agree before manufacture
- Identify product evidence for the actual window configuration.
- Mark the building air-barrier line on installation sections.
- Detail corners, supports and penetrations through the seal.
- Confirm material compatibility and installation responsibilities.
- Agree inspection and testing stages before finishes close.
- Record authorised repairs and final acceptance evidence.
A question to resolve early
Will a good window air-permeability class ensure the building passes its test?
It cannot establish that result by itself. The installed perimeter joints and the rest of the enclosure must also meet the project design, and the completed building needs the agreed verification.
Manufacturer reference
AWS 90.SI+ is presented by Schüco within its highly insulated aluminium window range; actual performance evidence must match the selected configuration. Schüco: AWS 90.SI+.
This reference illustrates a manufacturer’s system approach. Confirm availability, applicable documentation and the final configuration with the project supplier.
Related technical guides
Discuss your project with Alumproof
Send your drawings, project location and required performance. We can review the information and clarify the system configuration and quotation scope.
All technical guides · Technical support for architects · Explore aluminium systems